MO status before rescheduling: start- and finish date = 24/04/20 / quantity = 18000
MO material lines and operations before rescheduling
Select the MO + option 21 - reschedule
Quantity and/or dates can be changed in PMS010
Only Start or Finish date can be entered, since M3 will recalculate the production lead time, since quantity has been changed.
Refresh view (F5) in PMS100 – changes are as to be expected for the MO header and lines.
Remark: M3 does not allow to reschedule an MO if the picking list already exists => deletion of picking list required to proceed.