Goods Receiving Method in the Purchase order

 

In the purchase order flow, the goods receiving method (GRM)defines how to proceed with the goods receiving, the inspection and the put-away steps:

 

 

  1. Goods Receiving Method (PPS345)

The goods receiving method (GRM) specifies how the goods should be treated in the receiving flow. For example:

- Is direct put-away used?

- Is quality inspection done before putting away?

There are few goods receiving methods used in Kemin.

 

 

  1. Goods Receiving Method in the PO line (PPS201/F)

The goods receiving method defines how the system will process the goods receipt of an item in a PO. It is set on the PO line.

 

  1. Goods Receiving Method in the Item/Supplier Master Data (PPS040/E)

The goods receiving method that will be set in the PO line comes from the connection Item/Supplier, PPS040.

 

 

  1. GRM used in Kemin:

 

DIR – (DIRECT PUT AWAY) – Used for items with not inspection (expenses, services, etc)

 

SUB – (Subcontracting) – Used in the subcontracting process (Tollers)

 

RIP – Used for inventory items with Quality Control – The goods are received, then inspected and then put away.

 

RI - Used for inventory items with Quality Control – The goods are received, then inspected. There is no put away step in this GRM.

 

RPI, RP7 and RPS - Used for inventory items with Quality Control but in this case the put away step is done before doing the inspection.

 

 

 

 